Scott Bateman School Boiler Replacement

Description:

New Building Automation System utilizing Reliable Controls© products, Mach Pro Com, and Mach Pro Sys. The project included two new electronic Precision boilers, 5 new pumps with ABB VFD’s, new temperature and pressure sensors, and re-use of the existing propane boiler.

The new boilers were integrated via Modbus, and the VFD’s via BACnet, both MS/TP. The system is native BACnet web browser access, 3D graphical interface, operator workstation, trending, custom scheduling and programming.

Project Info

  • Owner::
    Kelsey Scool Division
  • Project : :
    Scott Bateman School Boiler Replacement
  • Location: :
    The Pas, MB
  • General Contractor::
    Neepawa Plumbing and Heating
  • Consultant: :
    MCW/AGE